Project: Nanuya Island Repower
Customer: Nanuya Island Resort Fiji
Scope: Nanuya Island Resort had been reporting power issues on their site. Their primary
generator was replaced with a Cummins C170D5. The site has a 96Kw SMA Sunny Island system with 115Kw of solar. The Island system was behaving erratically and power dropouts were constant. After reprograming the system and recalibrating the controllers, the system operated again with full autonomy.
Project: DSE 5510-8610 Control System Replacement & Integration
Customer: IHG Group
Scope: IHG Intercontinental resort had two failed DSE 5110 controllers. The site had recently had the alternators rewound and needed them installed and commissioned as part of this project. The DSE 5510 was removed and the new DSE8610 were installed. While onsite, API carried out a HV system audit and updated their HV single-line diagrams
Finding Energy Management Solutions
ABN: 73 619 239 440
CONTRACTORS LIC NO: 312426C